Hi, the only time I've experienced this similar issue, is in production where
I was trying to overwrite an existing report, but the report was in use by
the end-users. Usually these reports were very large and required large
amounts of run time as well, since the timeout for deployment wasn't as long
as the runtime (so the report was in use during the entire span and couldn't
be deployed). Usually I would just wait a few minutes and I could redeploy
again without fail.
[quoted text, click to view] "Phil Koay" wrote:
> siaj,
>
> Thanks for the reply. But I'm afraid I can connect to the server but still
> am having the timeout issue.
>
> Cheers
>
> Phil.
>
> "siaj" <siaj@discussions.microsoft.com> wrote in message
> news:D77EB16F-9EAC-45CA-B766-2D4C91F7DA8C@microsoft.com...
> > Is your VS IDE and the report manager on a different machine? If that is
> the
> > case I think that your development machine is not able to connect to the
> > reort deployement machine. Try to browse the deployment server from your
> > development machine... http:\\<deployment machine name>\reportserver
> >
> > Let us know if it helps
> >
> > siaj
> >
> > "Phil Koay" wrote:
> >
> > > Hi there!
> > >
> > > Had a problem delopying the reports from the VS IDE. It kept coming up
> with
> > > an error "The operation has timed-out.". I ended up updating it via the
> > > 'report manager', this worked fine. I was wondering what I need to
> change in
> > > the VS IDE so that the deploy would work from there.
> > >
> > > Also thanks for your help in the past! Its an awsome product!
> > >
> > > Cheers
> > >
> > > Phil.
> > >
> > >
> > >
> > >
>
>